Droit Immobilier

Acceptance of Works Must Be Declared

📅 Décision du 24 June 1992⚖️ Cour de cassation📖 2 min de lecture

Acceptance of works, which must be made on an adversarial basis, is characterised by the client’s unequivocal intention to accept the works; this legally justifies the decision of the Court of Appeal, which excluded or limited the insurers’ guarantee for lack of acceptance, after noting that the fact that the works were continued by successive contractors did not establish the existence of an implied acceptance of the executed works, and held that, due to the absence of any record of the executed work sections and the clients’ initial claim for reimbursement of the advance payments made on the works carried out, their intention to accept those works was not established.

Reference decision: cc • No. 90-19.493 • 1992-06-24 • View the decision →

This decision sheds important light on your property law. Here is what it changes for you.

The situation

Acceptance of works, which must be made on an adversarial basis, is characterised by the client’s unequivocal intention to accept the works; this legally justifies the decision of the Court of Appeal, which excluded or limited the insurers’ guarantee for lack of acceptance, after noting that the fact that the works were continued by successive contractors did not establish the existence of an implied acceptance of the executed works, and held that, due to the absence of any record of the executed work sections and the clients’ initial claim for reimbursement of the advance payments made on the works carried out, their intention to accept those works was not established.

What the law says

This decision confirms the fundamental principles of property law.

Points to remember

  • Strictly respect the legal time limits for appeals
  • Keep all your supporting documents (deeds, instruments, letters)
  • Anticipate: preventive advice always costs less than litigation

For an analysis of your situation: 30-minute consultation at €45 with Maître Zakine.

📌 Does this apply to your situation? Maître Cécile Zakine, French real estate lawyer, practises throughout France.
→ Prendre RDV pour une consultation droit du travail  |  → Browse all our legal articles

Informations juridiques

  • Numéro: 90-19.493
  • Juridiction: Cour de cassation
  • Date de décision: 24 juin 1992

Mots-clés

droit immobilierjurisprudenceimmobilier

Cas d'usage pratiques

1

Renovation works halted, insurance refuses cover due to lack of acceptance

A homeowner in Lyon hired a builder for a €60,000 extension. After the builder left the project unfinished, a second contractor completed the work. The homeowner then claimed on their structural damage insurance for defects, but the insurer denied the claim because there was no formal acceptance document for the initial works.

Application pratique:

This case law shows that continuing works with a second contractor does not imply acceptance of the first contractor's work. To protect yourself, always conduct a joint inspection (adversarial basis) with the contractor and sign a formal acceptance record, even for partial works. Without this, insurers may refuse to cover defects. If you have already taken over work without acceptance, gather any evidence of your intention to accept or reject, such as written complaints or payment records, and consider legal advice immediately.

2

New buyer unaware that previous works were never formally accepted

A first-time buyer in Bordeaux purchased a flat where the previous owner had started a loft conversion costing €25,000, with part of the work done by an initial contractor who was replaced. The buyer completed the conversion, but later discovered leaks. The insurer refused the claim, stating that the original works were never formally accepted.

Application pratique:

When buying a property with recent or ongoing works, ensure you obtain all acceptance records from the seller. If none exist, you risk being unable to claim on insurance for defects in those works. Before purchase, request an adversarial inspection of the works with the contractors to formalise acceptance. This case clarifies that you cannot rely on implied acceptance; you need a clear record. If you've already bought, you may need to prove your own acceptance or lack thereof to insurers.

3

Syndic fails to formalise acceptance of common area works

In a co-ownership building in Nice, the syndic (property manager) hired successive contractors to repair the roof, each doing part of the work, totalling €80,000. When leaks reappeared, the co-owners' insurance claim was rejected because there was no acceptance record for each work section, and the syndic had not ensured adversarial acceptance.

Application pratique:

This decision highlights that even for large common area projects, acceptance must be formalised step by step. As a co-owner, insist that the syndic arranges formal acceptance inspections with each contractor before they leave the site. Without these records, your building's insurance may not cover defects. If your syndic has failed to do this, you may need to take collective action to regularise the situation and hold the syndic accountable. Keep all minutes of meetings where works were discussed as evidence of intentions.

Maître Cécile Zakine

À propos de l'auteur

Maître Cécile Zakine — Avocate au Barreau des Alpes-Maritimes, Docteur en Droit. Chaque article de ce magazine est rédigé à partir de l'analyse d'une décision de jurisprudence réelle, commentée et mise en perspective par les équipes de Maître Zakine.

Prendre rendez-vous →

Avertissement: Les analyses présentées sur ce site sont fournies à titre informatif uniquement et ne constituent pas des conseils juridiques personnalisés. Pour une consultation adaptée à votre situation, contactez un avocat.

★★★★★4.9/5 — Avis Google

Maître Zakine, Doctor of Law

Phone and video consultations available — Fast appointments

Book an appointment
First consultation 30 minutes — €45

🔒 Confidentiel • Sans engagement • Réponse rapide