By application of Article L
Droit Immobilier

By application of Article L

📅 Decision of 18 January 2006🔄 Updated on 16 October 2026⚖️ Cour de cassation👁️ 47 views📖 2 min read

By application of Article L. 261-13 of the Construction and Housing Code, purchasers of a building to be constructed who, in order not to pay the sums due under a formal notice to pay that has been served on them, raise a defence of non-performance, must apply to the court within one month to seek a suspension of the effects of the formal notice, failing which the resolutory clause is automatically triggered.

Reference decision: cc • No. 05-14.971 • 2006-01-18 • View decision →

This decision provides important insight into your property law rights. Here is how it affects you.

The situation

By application of Article L. 261-13 of the Construction and Housing Code, purchasers of a building to be constructed who, in order not to pay the sums due under a formal notice to pay that has been served on them, raise a defence of non-performance, must apply to the court within one month to seek a suspension of the effects of the formal notice, failing which the resolutory clause is automatically triggered.

What the law says

This decision confirms the fundamental principles of property law.

Key points to remember

  • Strictly observe the statutory time limits for seeking recourse
  • Keep all your supporting documents (title deeds, contracts, correspondence)
  • Plan ahead: preventive legal advice is always cheaper than litigation

For an analysis of your situation: 30-minute consultation for €45 with Maître Zakine.

📌 Does this apply to your situation? Maître Cécile Zakine, French real estate lawyer, practises throughout France.
→ Prendre RDV pour une consultation droit du travail  |  → Browse all our legal articles

Legal information

  • Number: 05-14.971
  • Court: Cour de cassation
  • Decision of: 18 January 2006

Keywords

droit immobilierjurisprudenceimmobilier

Practical use cases

1

First-time buyer misses deadline after finding defects

A couple in Paris purchased an off-plan apartment for €450,000. Upon receiving a formal notice demanding a €90,000 progress payment, they notice cracks and water damage in the structure and refuse to pay. They wait for the developer to respond, but do not approach the court within one month.

Practical application:

Under the case law, they were required to apply to the court for a suspension of the formal notice within 30 days. To avoid automatic contract termination and potential loss of their deposit, they must urgently file a court application (référé-suspension) with evidence of the defects. Seeking immediate legal advice is essential to preserve their rights and argue non-performance.

2

Investor withholds payment over construction delays

An investor bought two off-plan flats in Nice for €700,000. After receiving a formal notice for a €140,000 instalment, he delays payment, citing the developer's missed deadlines and slow progress. He does not apply to court, believing the developer’s breach excuses his non-payment.

Practical application:

The one-month deadline to seek court suspension is absolute, even if the developer is allegedly in breach. The investor must immediately instruct a French avocat to file an urgent suspension application and submit evidence of delays. Without this step, the developer can cancel the sale, and the investor risks losing both flats and being liable for damages.

3

Co-owner disputes final payment over common area defects

In a new-build co-ownership in Lyon, Mr. Martin withholds the final €25,000 payment on his €300,000 flat due to unresolved lift and fire safety issues in the common areas. He ignores a formal notice from the developer, assuming the co-owners’ association will collectively resolve the dispute.

Practical application:

Each buyer must act individually within one month of the formal notice. Mr. Martin should urgently file a court application for suspension, detailing the common-area defects and their impact on his flat. While coordinating with the co-owners’ association, he must not miss the judicial deadline to prevent automatic cancellation of his purchase contract.

Maître Cécile Zakine

About the author

Maître Cécile Zakine — Lawyer at the Alpes-Maritimes Bar, Doctor of Law. Every article in this magazine is based on the analysis of a real court decision, commented and put into perspective by Maître Zakine’s team.

Book an appointment →

Disclaimer: The analysis presented on this site is for informational purposes only and does not constitute personalised legal advice. For advice tailored to your situation, contact a qualified lawyer.

★★★★★4.9/5 — Google Reviews

Does this affect you?

Consult Maître Zakine — lawyer, Doctor of Law. Fast, clear answer.

Book a consultation →

🔒 Confidential · No obligation

📬 Get legal updates

One legal analysis per week, straight to your inbox. Free, no spam.

🔒 1-click unsubscribe · GDPR compliant

★★★★★4.9/5 — Avis Google

Maître Zakine, Doctor of Law

Phone and video consultations available — Fast appointments

Book an appointment
First consultation 30 minutes — €45

🔒 Confidentiel • Sans engagement • Réponse rapide