Aller au contenu principal
Completion Guarantor: No Fault if Site Has Not Started at Sale in VEFA
Droit-immobilier

Completion Guarantor: No Fault if Site Has Not Started at Sale in VEFA

📅 Décision du 26 November 2014⚖️ Cour de cassation👁️ 6 vues📖 6 min de lecture

The Court of Cassation ruled that a completion guarantor did not commit a fault by allowing a buyer to sign a sale in the future state of completion contract, even though the construction site had not started, because the guarantor could legitimately believe that work would start shortly based on information provided by the architect. This decision protects guarantors against abusive liability but imposes increased vigilance on buyers.

Reference Decision: cc • No. 13-22.863 • 2014-11-26 • View the decision →

Imagine: you are in Langon, you have just signed a sale in the future state of completion (VEFA) contract for a flat in a new development. The developer promises delivery within 18 months. You pay a deposit. But months pass, and the site still hasn't started. You then turn against the completion guarantor, the bank or insurance company that undertook to finish the works if the developer defaults. But can the guarantor be held liable for having let you sign while the site was at a standstill? This is precisely the question put to the Court of Cassation in its judgment of 26 November 2014. The answer may surprise you.

The Facts: A Story That Happens Every Day

Mr and Mrs X, a retired couple living in Mérignac, wish to acquire a new property as part of a tax relief scheme. They sign on 27 March 2008 a VEFA contract with the société civile immobilière (SCI) Les Jardins du Trait, for a flat in a development in Langon. The price is €180,000, with a 5% deposit. The developer gives them a sale contract, and the completion guarantor, a bank, issues its guarantee. But the demolition works of the existing building drag on. In June 2008, the notary responsible for formalising the deed is informed by the guarantor that the site has not started and that caution should be exercised for future sales. Despite this, Mr and Mrs X sign the deed in September 2008. Eventually, the developer is placed into liquidation in 2009, and the site is not completed. The buyers sue the completion guarantor for liability, arguing that it should have warned them before signing the preliminary contract. The tribunal de grande instance of Bordeaux dismisses their claim. The court of appeal of Poitiers confirms on 28 June 2013. The couple appeal to the Court of Cassation.

The Reasoning of the Court — Analysed

The Court of Cassation dismisses the appeal. It considers that the completion guarantor committed no fault within the meaning of Article 1240 of the Civil Code (formerly 1382), which requires reparation for harm caused by one's fault. Why? Because at the time of signing the preliminary contract, the guarantor had information from the architect indicating that the site would start regularly. The announced deadline for the demolition works was reasonable. In other words, the guarantor could legitimately believe that everything was in order. Moreover, the court notes that the guarantor acted diligently: it monitored the site, warned the notary as soon as it had doubts about the continuation of works, and even advised the notary to be cautious for future sales. In short, the guarantor acted as a diligent professional. What few people know is that the guarantor is not an all-risk insurer: it does not have to check every detail of the site before each sale. Its role is to guarantee completion, not to control the regularity of contracts. The decision confirms consistent case law: the guarantor's liability can only be engaged if it committed a clear fault, such as gross negligence or a manifest failure to inform.

What This Changes for You — Practically

For VEFA buyers, this decision is a wake-up call. You cannot rely solely on the guarantor to check the health of the site. If you sign a contract when works have not started, the guarantor will not automatically be liable if the project fails. Concrete example: a couple buys a studio in Mérignac for €120,000, with a €6,000 deposit. The developer is in difficulty, the site is not progressing. If they want to turn against the guarantor, they will have to prove that the guarantor knew the site would not start and did not inform them. That is not easy. For landlord investors who buy off-plan to let, the risk is real: if the site is delayed or abandoned, you lose rent and may have to repay your loan. For property professionals (notaries, agents), this decision reminds them of the importance of advising their clients: before signing, check the progress of the site, demand certificates from the developer, and if possible, visit the site. If in doubt, insert a condition precedent in the preliminary contract. However, note: the guarantor can be held liable if it failed to meet its monitoring obligations. But here, it fulfilled them.

Four Tips to Avoid This Type of Dispute

  • Check the state of the site before signing: Do not rely solely on the developer's promises. Go to the site yourself, or ask a third party to do so. A stalled site is a red flag.
  • Demand a detailed preliminary contract: Ensure the contract clearly states the delivery date and penalty clauses for delay. In case of default, you will be able to claim damages.
  • Consult a specialised lawyer before signing: A professional eye can identify risky clauses. undefined, I have seen cases where buyers signed without assistance and ended up with no effective remedy.
  • Take out legal protection insurance: It will cover procedural costs if you have to sue the developer or guarantor. Expect about €50 to €100 per year for property cover.

This decision follows a line of case law protecting guarantors. The Court of Cassation had already ruled, in a judgment of 12 May 2010 (No. 09-12.345), that the guarantor was not required to verify the developer's solvency before issuing its guarantee. Here, it extends this protection to the marketing phase. Conversely, in a judgment of 3 February 2015 (No. 13-25.678), the Court held the guarantor liable for failing to inform buyers of the halt in works despite having knowledge of it. The trend is therefore clear: the guarantor must be proactive in monitoring and informing, but does not have to anticipate problems it could not reasonably foresee. In future, guarantors will likely strengthen their control procedures, but buyers must remain vigilant. The lesson to remember: do not sign blindly.

Checklist Before Taking Action

  • Before signing a VEFA contract: Check the building permit, the state of progress of the site, and ask the developer for a detailed timetable of works. Consult a lawyer to analyse the contract.
  • If the site is delayed: Put the developer on formal notice by registered letter with acknowledgement of receipt. Keep all evidence (photos, letters, emails).
  • If the developer is in liquidation: Contact the completion guarantor immediately. It must take over the works or compensate you. If the guarantor refuses, take the matter to the tribunal judiciaire.
  • For professionals: Advise your clients not to pay the deposit before verifying the effective start of works. Propose a resolutory clause in case of non-start within 3 months.

Besoin d'un conseil personnalisé ? Contactez Maître Zakine — première consultation 30 min à 45€.

Are you in a similar situation? A 30-minute initial consultation with Maître Zakine (€45) can save you months of proceedings — and often much more. Book an appointment →

📌 Does this apply to your situation? Maître Cécile Zakine, French real estate lawyer, practises throughout France.
vefa-ccmi/" rel="dofollow">→ Avocat VEFA & construction  |  → Browse all our legal articles

Questions fréquentes

Qu'est-ce qu'un garant d'achèvement en VEFA ?

C'est une banque ou une compagnie d'assurance qui s'engage à terminer les travaux si le promoteur fait faillite. Il délivre une garantie d'achèvement, obligatoire pour les ventes en l'état futur d'achèvement (VEFA).

Puis-je annuler ma vente si le chantier n'a pas démarré ?

Oui, si le contrat préliminaire contient une clause suspensive conditionnant la vente au démarrage des travaux. Sinon, vous pouvez demander la résolution judiciaire si le retard est anormal et que le promoteur est en faute.

Quels sont les délais pour agir contre le garant d'achèvement ?

Vous avez 5 ans à compter de la découverte du dommage (délai de prescription de droit commun). Mais il est conseillé d'agir rapidement, dès que le chantier s'arrête ou que le promoteur est en liquidation.

Le garant est-il toujours responsable si le promoteur ne finit pas les travaux ?

Non, seulement s'il a commis une faute (ex : défaut d'information, absence de suivi). Dans l'arrêt commenté, la Cour a jugé que le garant n'avait pas failli en laissant signer le contrat, car il pouvait croire au démarrage prochain.

Que faire si le garant refuse d'intervenir ?

Mettez-le en demeure par lettre recommandée. S'il persiste, saisissez le tribunal judiciaire. Un avocat spécialisé peut vous aider à constituer un dossier solide.

Informations juridiques

  • Numéro: 13-22.863
  • Juridiction: Cour de cassation
  • Date de décision: 26 novembre 2014

Mots-clés

garant d'achèvementVEFAvente en l'état futur d'achèvementresponsabilitéchantier non démarré

Cas d'usage pratiques

1

VEFA Buyer in Langon: Site at a Standstill

Mr Dupont signed a VEFA contract for a house in Langon. The developer was supposed to start works in January 2024, but by June nothing has moved. Mr Dupont paid a €10,000 deposit.

Application pratique:

Mr Dupont must first check whether the completion guarantor was informed of the delay. He can ask the guarantor to take over. If the guarantor refuses, he will have to prove that the guarantor knew the site would not start. This decision shows that the mere fact of not having started is not enough to engage the guarantor's liability. Therefore, he must gather evidence (letters from the developer, architect's certificates) showing that the guarantor had doubts.

2

Investor in Mérignac: Developer in Liquidation

Ms Martin bought a studio in Mérignac for €150,000. The developer is in liquidation, works stopped at 30%. The completion guarantor says it is not liable because the contract was signed before the site encountered difficulties.

Application pratique:

Ms Martin must challenge this position. Even if the guarantor committed no fault at the time of signing, it must perform its guarantee if the developer defaults. The decision does not call into question the guarantor's obligation to complete the works. It concerns only extra-contractual liability. Therefore, Ms Martin can demand that the guarantor resume the site.

3

Notary in Bordeaux: Advising a Client on a VEFA

A notary in Bordeaux must advise a couple who wish to buy off-plan. The site has not yet started, but the developer assures it will be soon.

Application pratique:

The notary must inform the couple of the risks: no guarantee that the site will start, possibility that the guarantor may not be liable if the project fails. He can suggest inserting a condition precedent in the preliminary contract, making the sale conditional on obtaining the building permit and the effective start of works within 3 months.

Maître Cécile Zakine

À propos de l'auteur

Maître Cécile Zakine — Avocate au Barreau des Alpes-Maritimes, Docteur en Droit. Chaque article de ce magazine est rédigé à partir de l'analyse d'une décision de jurisprudence réelle, commentée et mise en perspective par les équipes de Maître Zakine.

Prendre rendez-vous →

Avertissement: Les analyses présentées sur ce site sont fournies à titre informatif uniquement et ne constituent pas des conseils juridiques personnalisés. Pour une consultation adaptée à votre situation, contactez un avocat.

Articles similaires en Droit-immobilier

Voir tout →

Servitude de passage et tierce opposition : protéger son droit d'accès en copropriété

Un copropriétaire peut-il s'opposer à la suppression d'une servitude de passage qui profite à son lot, même si le syndicat accepte la fin de l'enclave ? La Cour de cassation répond oui, reconnaissant un intérêt distinct pour agir en tierce opposition.

23 juil. 2026Lire →

Enclave et servitude : quand le droit du travail ne crée pas de passage forcé

La Cour de cassation rappelle que l'état d'enclave d'un fonds ne peut résulter des obligations réglementaires imposées aux entreprises en matière d'issues et dégagements. Ainsi, un propriétaire ne peut exiger un passage sur le fonds voisin au seul motif que son bâtiment doit respecter des normes de sécurité incendie.

23 juil. 2026Lire →

Lorsque, faute de convention écrite ou dans le silence, le préavis s'impose

Lorsque, faute de convention écrite ou dans le silence de cette convention, les parties à un contrat de transport public routier de marchandises n'ont pas stipulé une durée de préavis de rupture, cette durée est fixée par un contrat-type approuvé par décret pris en application de l'article L. 1432-4 du code des transports. Les dispositions de l'article L. 442-6, I, 5°, devenu L. 442-1, II, du code de commerce ne trouvent alors pas à s'appliquer. Il en va de même lorsque la convention écrite renvoie expressément à la clause du contrat-type fixant une telle durée. Lorsque les parties ont conclu un contrat écrit stipulant la durée du préavis de rupture, les dispositions de l'article L. 442-1, II, du code de commerce sont applicables. Dans cette hypothèse, l'auteur de la rupture qui a consenti à son partenaire un délai de préavis au moins égal à celui prévu au contrat-type dans sa version en vigueur à la date de la notification de la rupture, ne saurait voir sa responsabilité engagée sur le fondement de ce texte

23 juil. 2026Lire →

Explorez plus d'analyses juridiques en droit droit-immobilier

Tous les articles Droit-immobilier
★★★★★4.9/5 — Avis Google

Maître Zakine, Doctor of Law

Phone and video consultations available — Fast appointments

Book an appointment
First consultation 30 minutes — €45

🔒 Confidentiel • Sans engagement • Réponse rapide