📅 Décision du 24 March 1982⚖️ Cour de cassation👁️ 6 vues📖 2 min de lecture

Lack of legal basis of the judgment which, in order to declare time-barred due to the expiry of the two-year guarantee period an action for the repair of defects, merely holds that the acceptance dates back to the date of provisional acceptance without investigating whether the execution of the works satisfied the reservations, set out in the subsequent final acceptance record and referred to in the submissions.

Reference decision: cc • N° 80-16.244 • 1982-03-24 • Consult the decision →

This decision provides important insight into your property rights. Here is what it changes for you.

The situation

The judgment lacks legal basis which, in order to declare time-barred due to the expiry of the two-year guarantee period an action for the repair of defects, merely holds that the acceptance dates back to the date of provisional acceptance without investigating whether the execution of the works satisfied the reservations, set out in the subsequent final acceptance record and referred to in the submissions.

What the law says

This decision confirms the fundamental principles of property law.

Key takeaways

  • Strictly comply with legal deadlines for appeals
  • Keep all your supporting documents (deeds, instruments, correspondence)
  • Plan ahead: preventive advice always costs less than litigation

For an analysis of your situation: 30-minute consultation at €45 with Maître Zakine.

📌 Does this apply to your situation? Maître Cécile Zakine, French real estate lawyer, practises throughout France.
→ Prendre RDV pour une consultation droit du travail  |  → Browse all our legal articles

Informations juridiques

  • Numéro: 80-16.244
  • Juridiction: Cour de cassation
  • Date de décision: 24 mars 1982

Mots-clés

droit immobilierjurisprudenceimmobilier

Cas d'usage pratiques

1

First-time buyer facing two-year guarantee expiry

A couple in Lyon purchased a newly built house in 2021. Provisional acceptance was signed on 1 March 2021 with reservations about cracking walls. The developer only partially fixed them, and in 2023, more cracks appeared. The developer claims the two-year guarantee expired in March 2023.

Application pratique:

Under the case law, the two-year guarantee does not automatically start from provisional acceptance if reservations were not fully satisfied. You should obtain the final acceptance record and any correspondence about the unresolved reservations. Notify the developer in writing that the guarantee period only begins once the reserved defects are properly repaired, so your claim is still valid. Seek legal advice immediately to assert your right to repairs under the guarantee.

2

Landlord's rental property with persistent plumbing defects

An investor in Bordeaux bought an off-plan flat in 2020 for rental income. Provisional acceptance was on 15 June 2020 with reservations about faulty plumbing. The builder's partial repairs failed, and a major leak occurred in July 2022. The builder argues the two-year guarantee expired in June 2022.

Application pratique:

This case law clarifies that the guarantee's starting point is not the provisional acceptance if reservations remained unresolved. Collect all evidence proving the plumbing issues were part of the original reservations and were never fully rectified. Formally notify the builder that the guarantee period was suspended until proper completion of the reserved works, making your July 2022 claim timely. Consider consulting a solicitor to initiate legal proceedings if the builder refuses to undertake the necessary repairs.

3

Co-owners dispute over water infiltration guarantee deadline

In a new block of flats in Nice, co-owners have experienced water infiltration in the underground car park since completion in 2019. Provisional acceptance in September 2019 included reservations about waterproofing. The developer's attempts failed, and in February 2022, the syndic wanted to sue, but the developer claimed the two-year guarantee had expired.

Application pratique:

According to the precedent, the two-year period does not commence from provisional acceptance when reservations like waterproofing are not fully resolved. The syndic must review the final acceptance report to confirm whether the reservation was ever lifted. Write to the developer stressing that the guarantee period started only when the waterproofing was adequately fixed, which has not yet occurred, so the claim is not time-barred. Engage a lawyer to represent the co-owners collectively and pursue compensation or repairs through legal channels.

Maître Cécile Zakine

À propos de l'auteur

Maître Cécile Zakine — Avocate au Barreau des Alpes-Maritimes, Docteur en Droit. Chaque article de ce magazine est rédigé à partir de l'analyse d'une décision de jurisprudence réelle, commentée et mise en perspective par les équipes de Maître Zakine.

Prendre rendez-vous →

Avertissement: Les analyses présentées sur ce site sont fournies à titre informatif uniquement et ne constituent pas des conseils juridiques personnalisés. Pour une consultation adaptée à votre situation, contactez un avocat.

Articles similaires en Immobilier

Voir tout →

Il résulte des décisions de la Cour de justice des Communautés européennes que l'obligation qui pourrait peser sur la SACEM de justifier l'importance des redevances qu'elle réclame aux discothèques, suppose que les contrefacteurs aient préalablement démontré que ces redevances sont sensiblement plus élevées que celles pratiquées dans les autres Etats membres du Marché commun, cette différence ne pouvant constituer l'indice d'un abus de position dominante que dans la mesure où la comparaison des niveaux de tarifs aurait été effectuée sur une base homogène.

18 août 2026Lire →

SI L'ALINEA 4 DE L'ARTICLE 21 DE L'ORDONNANCE DU 23 OCTOBRE 1958 FIXE DES LIMITES AU JUGE POUR APPRECIER LA VALEUR DE L'IMMEUBLE EXPROPRIE AU CAS OU CELUI-CI A FAIT L'OBJET D'UNE MUTATION ANTERIEURE DE MOINS DE CINQ ANS A LA DECISION, L'EXCEPTION AU PRINCIPE DE CE PLAFOND PREVUE POUR LE CAS DE MODIFICATION DANS LA CONSISTANCE OU L'ETAT DES LIEUX ET LA REVISION DE L'ESTIMATION ANTERIEURE INSCRITES DANS UN SEUL ET MEME PARAGRAPHE D'ARTICLE, ONT POUR FONDEMENT COMMUN LA VOLONTE DU LEGISLATEUR DE NE POINT PRIVER L'EXPROPRIE DE LA PLUS VALUE ACQUISE PAR LES IMMEUBLES DEPUIS LEUR DERNIERE MUTATION. LES JUGES DU FOND PEUVENT CONSIDERER COMME UNE MODIFICATION DANS LA CONSISTANCE DES LIEUX UN CHANGEMENT SURVENU DANS L'INTERET S'ATTACHANT A L'EMPLACEMENT DES IMMEUBLES, PARTICULIEREMENT DANS LE CAS OU LE QUARTIER DES IMMEUBLES EXPROPRIES S'EST TRANSFORME RAPIDEMENT DE ZONE RURALE EN ZONE INDUSTRIELLE.

18 août 2026Lire →

La requalification d'un contrat à

La requalification d'un contrat à durée déterminée en contrat à durée indéterminée ne porte que sur le terme du contrat et laisse inchangées les autres stipulations contractuelles. Doit être cassé l'arrêt qui, pour fixer une rémunération mensuelle de référence et, par suite, les sommes dues au salarié en conséquence de la requalification de la relation de travail en un contrat à durée indéterminée, relève que l'examen des bulletins de paie montre qu'à compter du mois de janvier 2013 l'employeur a baissé le nombre des jours de travail, et cela jusqu'au 31 mai 2015, alors que la détermination des jours de travail, qui résultait de l'accord des parties lors de la conclusion de chacun des contrats à durée déterminée, n'était pas affectée par leur requalification en un contrat à durée indéterminée

18 août 2026Lire →

Explorez plus d'analyses juridiques en droit immobilier

Tous les articles Immobilier
★★★★★4.9/5 — Avis Google

Maître Zakine, Doctor of Law

Phone and video consultations available — Fast appointments

Book an appointment
First consultation 30 minutes — €45

🔒 Confidentiel • Sans engagement • Réponse rapide