Works Contract Without Fixed Price: When the Contractor Commits to a Maximum Price
Droit-immobilier

Works Contract Without Fixed Price: When the Contractor Commits to a Maximum Price

📅 Décision du 22 June 1976⚖️ Cour de cassation👁️ 12 vues📖 8 min de lecture

The French Supreme Court (judgment of 22 June 1976) validates that a works contract may not be a fixed-price contract while still containing the contractor's commitment not to exceed a certain price. This means that the client may be required to pay for overruns, unless there is prior written agreement on additional works. A key decision for any owner undertaking works, in Clermont-Ferrand as elsewhere.

Reference decision: cc • No. 75-11.612 • 1976-06-22 • View decision →

You are the owner of a flat in Chamalières and you entrust a company with the renovation of your bathroom. The initial estimate is €8,000, but during the works, the contractor discovers a pipe that needs replacing. He tells you: 'Don't worry, I'll stay within the €8,000 budget.' Yet the final bill rises to €10,500. What should you do? Do you have to pay everything? And if the contract does not specify that the contract is a fixed-price contract, who should bear the excess?

This question is asked by hundreds of owners and contractors every year. The French Supreme Court answered it in a judgment of 22 June 1976, which is still relevant today. It ruled that a works contract may not be a fixed-price contract (i.e., at a fixed and final price) while still containing the contractor's commitment to build without exceeding a certain price. In other words, the contractor may be bound by a cap, but the contract remains 'measure and value': additional works not foreseen must be accepted by the client to be paid.

This decision protects the owner against nasty surprises, but it also imposes vigilance: any overrun must be formalised in writing. Otherwise, the contractor risks not being paid for the extras. Let's delve into this case, which took place in Paris, but whose lessons apply to everyone, from Clermont-Ferrand to Lyon.

The facts: a story like many that happen every day

In 1971, the company Rivoli Saint-Jacques, which operates a shop in Paris, entrusts the company Caillette et Dony with structural works in its commercial premises. The accepted estimate amounts to a certain sum, but during the works, additional works become necessary. The company carries them out without obtaining a new estimate signed by the client. At the end, it claims payment for these additional works, i.e., an amount exceeding the initial estimate.

The company Rivoli Saint-Jacques refuses to pay, arguing that the contract was a fixed-price contract and that any overrun had to be authorised in writing. The company Caillette et Dony brings the case before the commercial court, then the Paris Court of Appeal. In 1975, the Court of Appeal rules in favour of the contractor: it considers that the contract was not a fixed-price contract, but a 'measure and value' contract with a maximum price. The contractor was entitled to be paid for the additional works, even without a written variation order.

The company Rivoli Saint-Jacques appeals to the Supreme Court. It argues that any works contract is by nature a fixed-price contract, and that overruns must be accepted by the client. The French Supreme Court, in its judgment of 22 June 1976, dismisses the appeal. It confirms that 'a works contract may not have the character of a fixed-price contract while containing the contractor's commitment to build without the cost of construction exceeding a certain price'. Thus, the Court of Appeal correctly applied the law of the parties (the will of the contracting parties) by refusing the contractor payment for unauthorised additional works.

Note: The Supreme Court dismissed the appeal, but in favour of the contractor? No, in fact it validated the reasoning of the Court of Appeal, which had rejected the contractor's claim for unauthorised overruns. The judgment is therefore favourable to the client: without written agreement, the contractor cannot claim the excess.

The reasoning of the court — broken down

The Supreme Court relies on Article 1134 of the Civil Code (now Article 1103 since 2016), which provides that 'legally formed agreements take the place of law for those who have made them'. In everyday language: the contract is law between the parties. Judges must respect the will expressed in the contract, without adding conditions that the parties did not foresee.

Here, the contract between Rivoli Saint-Jacques and Caillette et Dony did not stipulate that the contract was a fixed-price contract. It only set a maximum price not to be exceeded. The Court of Appeal interpreted this clause as a cap, but not as a fixed and final price. Therefore, the contractor could charge for additional works, provided they had been accepted by the client. However, in the absence of written acceptance, these works were not due.

Rivoli Saint-Jacques argued that any construction contract is by nature a fixed-price contract, which is a misconception. The Supreme Court sweeps this aside: nothing in the law requires a works contract to be a fixed-price contract. The parties are free to choose a 'measure and value' contract, with a maximum price, or even without a predetermined price. What matters is what they intended.

This judgment does not create a change in case law: it confirms a classic solution. On the other hand, it reminds us of a fundamental principle: the fixed-price nature of a contract is not presumed. If the contract does not expressly say 'fixed-price contract', it is considered 'measure and value'. For contractors, this is a warning: without a written variation order, overruns risk remaining unpaid. For owners, it is a protection: they only have to pay what they have accepted.

What this changes for you — concretely

For the owner carrying out works: if you sign an estimate without mentioning 'fixed-price', the contractor may charge you for additional works, but only if you have accepted them in writing. In practice, be wary of oral 'little extras'. A contractor tells you 'I'll change this socket, it'll be included in the price'. If he does not note it down, you could receive an extra bill. Example: initial estimate €15,000 for a kitchen renovation in Clermont-Ferrand. During the works, the electrician adds three sockets and under-cabinet lighting. Without a signed variation order, you are not obliged to pay the additional €800. But be careful: if the works are essential (e.g., compliance with standards), the judge might consider them implicitly included.

For the contractor: this decision obliges you to formalise each modification. Do not rely on the client's good faith. Have a variation order signed before carrying out additional works. If the client refuses, you can stop the works or inform them that the cost will exceed the cap. Example: in Chamalières, a plumber carried out emergency works without a signed estimate. The client refused to pay half the bill. The court ruled in favour of the client, due to lack of written agreement.

For the co-owner: if you carry out works in your private parts, the same principle applies. But for common parts, it is the managing agent who represents the co-owners' association. Contractors must obtain a written order from the managing agent for any overrun. Otherwise, the association may refuse to pay.

Time limit to remember: the contractor's action for payment is barred after 5 years (general limitation period). If you receive a bill for unauthorised works, you can challenge it within this period.

Four tips to avoid this type of dispute

  • Require a written contract specifying whether it is fixed-price or not. If you want a fixed price, have 'fixed-price contract' written in and list all the services. This avoids any ambiguity.
  • For any additional work, sign a variation order before execution. Even for a small modification, get into the habit of writing an email or signing a purchase order. Example: in Clermont-Ferrand, a client refused to pay €200 for extra paint because the contractor had no written evidence. The court ruled in his favour.
  • Photograph the progress of the works. In case of dispute, dated photos prove what was done. Attach them to the estimates and variation orders.
  • Check the legal mentions of the estimate. The estimate must state the total price, the period of validity, and the payment terms. If it is vague, ask for written clarifications.

The 1976 judgment is part of a consistent line: the Supreme Court regularly reminds that the fixed-price nature of a contract is not presumed (Civ. 3e, 11 May 2000, no. 98-17.123). More recently, in a judgment of 16 June 2021 (no. 20-13.647), it ruled that the absence of mention of the fixed-price nature in an estimate is not sufficient to exclude a fixed price, if the parties agreed on a global and final price. In other words, everything depends on the will of the parties, expressed in the contract.

Another notable development: the Law of 17 June 2008 reduced the limitation period from 30 to 5 years for professionals' actions for payment. This reinforces the need to act quickly.

In practice, courts are demanding regarding proof of the client's agreement. A simple exchange of emails may suffice, but a signed writing is better. The trend is towards consumer protection: unfair terms in contracts for work are sanctioned. For example, a clause that would require the client to pay all overruns without their agreement would be deemed unwritten.

Key points to remember

Practical FAQ:

  • Is an estimate always a fixed-price contract? No. An estimate is a price offer, but the contract is only fixed-price if the parties have expressly agreed. In the absence of mention, the contract is 'measure and value'.
  • Can I refuse to pay for additional works not foreseen in the estimate? Yes, if you have not accepted them in writing. But if the works were essential for the proper performance of the contract, the judge might consider them included in the price.
  • What should I do if the contractor claims an overrun that I did not authorise? Challenge it in writing (registered letter with acknowledgement of receipt) stating the lack of agreement. If the contractor sues you, you will have a strong defence.
  • Can the contractor stop the works if I refuse an extra? Yes, if the extra is necessary and you refuse to pay. But he must put you on notice to accept the variation order. If he stops without notice, he may be liable for delay.

In summary: a works contract is not necessarily fixed-price. To avoid disputes, formalise everything in writing. That is the lesson from this 1976 judgment, still relevant today.

Do you find yourself in a similar situation? A first 30-minute consultation with Maître Zakine (€45) can save you months of proceedings — and often much more. Book an appointment →

📌 Does this apply to your situation? Maître Cécile Zakine, French real estate lawyer, practises throughout France.
→ Prendre rendez-vous pour une consultation  |  → Browse all our legal articles

Questions fréquentes

Un devis signé est-il toujours un marché forfaitaire ?

Non, un devis est une offre de prix, mais le caractère forfaitaire doit être expressément mentionné. Sans cette mention, le marché est considéré comme 'à façon', ce qui permet des ajustements de prix sous conditions.

Puis-je refuser de payer des travaux supplémentaires non prévus au devis initial ?

Oui, si vous ne les avez pas acceptés par écrit. L'entrepreneur doit obtenir votre accord exprès avant d'exécuter des travaux supplémentaires. En l'absence d'écrit, vous pouvez contester la facture.

Quels sont les délais pour contester une facture de travaux supplémentaires ?

L'action en paiement de l'entrepreneur se prescrit par 5 ans à compter de la fin des travaux. Vous pouvez contester dans ce délai, mais il est conseillé de le faire rapidement dès réception de la facture.

Que faire si l'entrepreneur réclame un paiement pour des travaux non autorisés ?

Envoyez une lettre recommandée avec accusé de réception contestant la facture, en rappelant l'absence d'accord écrit. Conservez tous les documents (devis, photos, échanges). Si nécessaire, consultez un avocat spécialisé.

Le caractère forfaitaire peut-il être implicite ?

La jurisprudence récente (Civ. 3e, 16 juin 2021) indique que l'absence de mention ne suffit pas à exclure un forfait si les parties ont convenu d'un prix global et définitif. Tout dépend de la volonté des parties, à prouver par écrits.

Informations juridiques

  • Numéro: 75-11.612
  • Juridiction: Cour de cassation
  • Date de décision: 22 juin 1976

Mots-clés

marché de travauxforfaitprix maximumtravaux supplémentairesCour de cassation 1976

Cas d'usage pratiques

1

Owner in Clermont-Ferrand: bathroom renovation with overrun

You sign an estimate of €8,000 to renovate your bathroom. The contractor discovers a pipe that needs replacing and tells you orally that it stays within the budget. Finally, the bill is €10,500.

Application pratique:

Without a written variation order, you can refuse to pay the additional €2,500. Send a written challenge and offer to pay only the initial amount. If the contractor insists, take the case to the local court in Clermont-Ferrand.

2

Contractor in Chamalières: carrying out additional works without written agreement

You are a contractor and you carry out additional works for a client, thinking they agree orally. The client refuses to pay the final bill of €12,000 instead of the €10,000 estimate.

Application pratique:

You will not be able to obtain payment for the additional €2,000 without written proof of the client's agreement. In future, have a variation order signed before any modification. In case of refusal, you can propose instalments or mediation.

3

Co-owner: works in common parts without written order

The managing agent orders roof works for €20,000. During the works, the company discovers leaks and carries out additional repairs for €3,000, without a written order from the managing agent.

Application pratique:

The co-owners' association can refuse to pay the €3,000. The managing agent must obtain written agreement from the council or the general meeting before any overrun. Without a writing, the company can only claim the excess from the managing agent personally.

Maître Cécile Zakine

À propos de l'auteur

Maître Cécile Zakine — Avocate au Barreau des Alpes-Maritimes, Docteur en Droit. Chaque article de ce magazine est rédigé à partir de l'analyse d'une décision de jurisprudence réelle, commentée et mise en perspective par les équipes de Maître Zakine.

Prendre rendez-vous →

Avertissement: Les analyses présentées sur ce site sont fournies à titre informatif uniquement et ne constituent pas des conseils juridiques personnalisés. Pour une consultation adaptée à votre situation, contactez un avocat.

Articles similaires en Droit-immobilier

Voir tout →

Servitude de passage et tierce opposition : protéger son droit d'accès en copropriété

Un copropriétaire peut-il s'opposer à la suppression d'une servitude de passage qui profite à son lot, même si le syndicat accepte la fin de l'enclave ? La Cour de cassation répond oui, reconnaissant un intérêt distinct pour agir en tierce opposition.

23 juil. 2026Lire →

Enclave et servitude : quand le droit du travail ne crée pas de passage forcé

La Cour de cassation rappelle que l'état d'enclave d'un fonds ne peut résulter des obligations réglementaires imposées aux entreprises en matière d'issues et dégagements. Ainsi, un propriétaire ne peut exiger un passage sur le fonds voisin au seul motif que son bâtiment doit respecter des normes de sécurité incendie.

23 juil. 2026Lire →

Lorsque, faute de convention écrite ou dans le silence, le préavis s'impose

Lorsque, faute de convention écrite ou dans le silence de cette convention, les parties à un contrat de transport public routier de marchandises n'ont pas stipulé une durée de préavis de rupture, cette durée est fixée par un contrat-type approuvé par décret pris en application de l'article L. 1432-4 du code des transports. Les dispositions de l'article L. 442-6, I, 5°, devenu L. 442-1, II, du code de commerce ne trouvent alors pas à s'appliquer. Il en va de même lorsque la convention écrite renvoie expressément à la clause du contrat-type fixant une telle durée. Lorsque les parties ont conclu un contrat écrit stipulant la durée du préavis de rupture, les dispositions de l'article L. 442-1, II, du code de commerce sont applicables. Dans cette hypothèse, l'auteur de la rupture qui a consenti à son partenaire un délai de préavis au moins égal à celui prévu au contrat-type dans sa version en vigueur à la date de la notification de la rupture, ne saurait voir sa responsabilité engagée sur le fondement de ce texte

23 juil. 2026Lire →

Explorez plus d'analyses juridiques en droit droit-immobilier

Tous les articles Droit-immobilier
★★★★★4.9/5 — Avis Google

Maître Zakine, Doctor of Law

Phone and video consultations available — Fast appointments

Book an appointment
First consultation 30 minutes — €45

🔒 Confidentiel • Sans engagement • Réponse rapide